Construction retentions exist for good reason: they protect the main contractor if defects emerge after practical completion. Typically 3-5% of the contract value, these funds should be released within 12 months of completing the work.
But in practice, retentions often become indefinite. We've seen subcontractors chasing retentions for 2, 3, even 5 years after finishing a job—money they're legally entitled to, tied up without justification.
Here are the five most common reasons retentions get stuck, and more importantly, what you can do to recover them.
The Project Never Reached Practical Completion
The Problem: If the overall project hasn't been signed off as "practically complete," your retention clock hasn't even started. This happens when main contractors delay PC certification—sometimes for years—while they tie up loose ends with other trades or negotiate variations.
Why It Happens: Main contractors often have little incentive to rush PC certification. They're not losing money; you are. Some deliberately stall to keep cash in their business.
The Solution: Review your contract terms carefully. Many standard forms (JCT, NEC) allow subcontractors to claim retentions based on sectional completion or when their specific works are finished, not when the entire project achieves PC. If your contract allows this, issue a formal notice referencing the relevant clause. If it doesn't, your leverage is weaker—but you can still push back by threatening adjudication over unreasonable delay.
Pro Tip: Always negotiate sectional completion clauses into your subcontract. This protects you from delays caused by other trades.
Alleged Defects (Real or Imagined)
The Problem: The main contractor claims there are defects with your work and withholds the retention until you fix them. Sometimes these are legitimate issues. More often, they're vague allegations without proper supporting evidence—used as a pretext to delay payment.
Why It Happens: It's an easy stalling tactic. A simple email saying "we've identified issues with the M&E installation" can buy the main contractor months of breathing room, especially if you don't challenge it immediately.
The Solution: Demand specifics. Under the Housing Grants, Construction and Regeneration Act 1996 (as amended), any deduction from monies owed—including retentions—must be supported by a valid withholding notice. This notice must:
- Be issued within the contractual timeframe (usually 5 days before payment is due)
- Clearly state the amount being withheld and why
- Reference the specific defects or contractual breaches
If they can't produce this, they're in breach. You can issue a notice of adjudication and pursue immediate payment. Most main contractors back down when faced with a properly drafted pre-action letter citing their failure to serve a valid withholding notice.
"In 80% of retention disputes we handle, the main contractor has never issued a compliant withholding notice. They're banking on subcontractors not knowing their rights."
— Lisa Moyo, Founder, Luum ResolutionsThe Main Contractor Has Cash Flow Problems
The Problem: The main contractor is using your retention to fund their own operations. This is more common than you'd think, especially among mid-tier contractors operating on thin margins.
Why It Happens: Retentions held across multiple projects can add up to significant working capital. When cash gets tight, these funds become an attractive—albeit illegal—lifeline.
The Solution: This is where things get tricky. If the main contractor is genuinely insolvent, pursuing them through adjudication might get you a judgment but not your money. Instead:
- Check for retention bonds: Some contracts require the main contractor to hold retentions in a separate trust account or provide a bond. If they haven't done this, you may have a claim against the employer directly.
- Escalate to the client: Send a polite letter to the project client/employer explaining the situation. They have a vested interest in ensuring their contractors don't abuse the payment chain, and they may pressure the main contractor to release funds.
- Consider statutory demand: If the debt is undisputed and over £750, you can issue a statutory demand. This puts the main contractor on a 21-day clock to pay or face potential winding-up proceedings. It's aggressive, but it works.
Administrative Incompetence
The Problem: Nobody at the main contractor's office actually knows the retention is due. The project manager who commissioned your work has moved on, the accounts team is overwhelmed, and your retention has fallen through the cracks.
Why It Happens: Construction companies have notoriously poor record-keeping, especially on smaller subcontract packages. After 12-18 months, your file is buried under newer projects.
The Solution: This is the easiest one to fix. Send a formal written request for payment, citing:
- The original contract reference
- The date of practical completion (or your completion date if sectional)
- The retention amount owed
- The relevant payment terms from your contract
Address it to multiple people: the original project manager, the commercial manager, and accounts payable. Copy the client if necessary. Most of the time, this prompts someone to actually look at the file and process the payment.
Document Everything: Keep meticulous records of when PC was achieved, when defects periods expired, and all correspondence about retentions. This evidence becomes crucial if you need to escalate.
Contractual Ambiguity
The Problem: The contract doesn't clearly define when retentions are due, or there's a dispute over whether the defects liability period has even started.
Why It Happens: Poorly drafted bespoke contracts, or amendments to standard forms that create contradictions. For example, one clause might say retentions are due 12 months after PC, while another refers to "final completion" without defining what that means.
The Solution: This is where you need legal interpretation. An experienced construction disputes consultant can review your contract and identify the strongest position. Often, ambiguities are resolved using the contra proferentem rule—meaning terms are interpreted against the party that drafted them (usually the main contractor).
If the ambiguity is severe, you might need adjudication to get clarity. But first, try a detailed letter setting out your interpretation with references to case law or industry standards (like the JCT guidance notes). Many disputes settle once the main contractor realizes their position is weak.
What To Do Right Now
Immediate Actions:
- Review your contract: Identify the exact retention release triggers and timeframes
- Calculate what's owed: Include any interest if your contract provides for it
- Send a formal demand: Reference the contract clauses and statutory rights
- Set a deadline: Give them 14 days to respond or pay
- Prepare evidence: Gather completion certificates, correspondence, and payment records
If you've done all this and still hit a wall, it's time to escalate. Adjudication in construction disputes is designed to be fast (28 days from notice to decision) and cost-effective compared to litigation. Most importantly, you don't pay if you lose—each party bears their own costs, making it a low-risk option for subcontractors.
Stuck Retention? We Can Help
We specialize in unsticking retentions for construction and M&E subcontractors. Get a free 48-hour ledger review—we'll tell you exactly what's owed and the fastest route to recovery.
Get Your Free ReviewThe Bottom Line
Retentions are your money. You've completed the work, served your time in the defects period, and earned the right to be paid. If a main contractor is withholding funds without proper justification, they're in breach—and you have multiple legal routes to force payment.
Don't wait another year hoping it resolves itself. The longer retentions sit unclaimed, the harder they become to recover. Start with a formal demand, escalate quickly if needed, and don't be afraid to use the legal tools available to you.
After all, they're holding your cash flow hostage. It's time to get it back.
